JKP Kraljeva Gora

Capacity check on the Kraljevo Gora system

MEASUREMENT OF AVAILABLE QUANTITIES OF WATER

Due to the need to measure the flow in order to assess the available quantities of water, as well as the condition of certain parts of the water supply system Public Utility Company "Kraljeva Gora" d.o.o. Han Pijesak contacted us again with a request for the mentioned works.

In mid-October, 24-hour flow measurements were performed at pre-determined temporary and control measuring points with ultrasonic portable flow meters AQF 2000.

Mjerač protoka AQF 2000

The flow meters are distributed from the Javornik reservoir along the entire network to the end consumers in the settlements of Džimrije, Mrkalji, Mironja and Ljeskovac, so that the condition of the water supply network could be better understood.

Mjerenje protoka

Based on the performed 24-hour measurements, as well as control current measurements, it is evident that there are evident losses on most parts of the pipeline network of the water supply network of JKP "Kraljeva Gora" Han Pijesak.

Mjerenje protoka u rezervoaru

They are especially pronounced in the lower lower parts, where the pressures are the highest and where the water supply network is the oldest, ie in the city center.

Vodovod Istočno Sarajevo

Measurement on the East Sarajevo water supply system

FLOW AND PRESSURE MEASUREMENT

Na osnovu potreba vršenja mjerenja protoka i pritiska u cilju sagledavanja raspoloživih količina vode, kao i stanja vodovodnog sistema sa filterskog postrojenja “Tilava” sa kojeg se snabdijeva veći dio opštine Istočno Sarajevo, izvršili smo u prvoj fazi početna terenska mjerenja protoka i pritisaka na unaprijed utvrđenim stalnim i privremenim-kontrolnim mjernim mjestima.

Mjerenje protoka

In order to fully understand the state of the network and the capacities available in the distribution of drinking water, in addition to measuring flow and pressure, which were used for analysis, from permanent measuring points, ie measuring DMA zones, measurements were performed with ultrasonic portable flow meters. as well as measurements with portable digital pressure gauges.

Mjerač protoka AQF 2000

Mjerenje pritiska

 

 

Pressure measurement on MMP1 was performed in the underground hydrant in the street of the First Sarajevo Brigade near "Adiko" bank in the time of 48 hours with a measurement interval of 1 min. 

After the pressure logger was dismantled, the data was read and diagrams were made.

In order to improve the situation in the water supply of KP "Vodovod i kanalizacija" a.d. East Sarajevo and maintained the trend of continuous water supply without reductions, it is necessary to implement measures and interventions on the existing water supply and communal infrastructure, and above all to strengthen the detection and elimination of failures in order to save the amount of water currently available.