At the spring near Shipovo, we performed control and flow measurement at catchments, despite very difficult hydrometeorological conditions. Due to the urgency and necessity of reviewing the situation on the mentioned network, we met the needs of our clients "KIV-ING" d.o.o. Banja Luka.
The flow measurement was performed on the water supply network which supplies the suburban settlement and the industrial forest complex. Although the conditions were very bad due to the snow, which covered the route of the pipeline as well as the catchment, the measurement was still performed. Due to poor conditions, the measurement was performed in a limited period of time.
Flow measurements were performed on the pipeline after catchment, as well as on the pipeline before the collection tank.
Condition analysis and remediation proposals
Based on the current flow measurement and the obtained results, as well as the needs of consumers, we performed a partial analysis of the network condition.
Proposals for rehabilitation works and bringing the spring into functional condition were also presented, in order to use the maximum capacity.
In the following period, after the stabilization of the weather, it is necessary to accurately locate the directions and connection point of the pipeline, as well as all-day flow measurements.
After measuring and analyzing the value of the night flow, the location of the losses on the pipeline will be located.